 |
Smoke Damage in Buildings |
 |
| |
Writen by: Jim Bagley, M.C.I.O.B., Senior Project Manager
Smoke damage can impact buildings to varying degrees. In some instance it is possible to simply paint over surfaces with a smoke sealant, in other instances in order to remove the contamination and prevent residual odor, removal of materials, particularly porous materials, can be necessary.
A 14 storey concrete high rise development in the BC interior was subjected to an arson event whilst under construction involving a stack of PVC tarpaulins that were stored in the basement parkade. The intense smoke damage from the fire affected seven storeys of the reinforced concrete framed building. At the time of the fire the lower seven floors had partially installed finishes which were also damaged by smoke. |
|
|
|
 |
Before clean up could begin, PHH ARC completed sampling for particulate and organic compounds to establish respiratory protection for the clean up crews. Once safe work practices had been established, restoration crews began dry ice blasting soot from the impacted concrete surfaces. Since the concrete surfaces would be covered by finishes in the occupied areas of the building, odor was the major concern for clean up. In order to minimize construction delays, we needed to find a way of predicting and measuring removal of fire damage so that persistent odors were diminished.
There were no established criteria for what constituted a “clean” or “dirty” surface, but the property insurance required that the building be restored to its pre-loss condition, We carried out parallel testing of soot contaminated surfaces by swab sampling for hydrocarbons and surface tape-lift particulate sampling to determine the most reliable and cost effective method of assessing contamination. Samples were collected from heavily contaminated surfaces and lightly contaminated surfaces. Control samples were collected from areas at sufficient distance to not have been impacted by smoke damage.
Hydrocarbon analysis did not prove to be a particularly useful indicator of potential contamination. Hydrocarbons were present in relatively low concentrations on heavily impacted surfaces in and adjacent to the parkade, but below detection limits on surfaces which visibly had some levels of
smoke damage.
Particulate characterization was however a consistent and predictable indicator of damage and subsequent cleanliness. Heavily impacted surfaces showed soot and combustion particles as the major components of particles on the tape-lift samples, and lightly visually impacted surfaces had soot as either major components or minor components. Un-impacted and reference
samples showed soot to be present in trace amounts or not at all.
These results suggested that trace levels of soot on a sample represented a “clean” surface whereas, major or minor levels represent a “dirty” surface. Based of the results of parallel analysis PHH ARC recommended that surface particulate sampling and comparison with benchmark soot levels would be a cost effective method of determining the effectiveness of cleaning surfaces.
The restoration contractor’s work crews performed the clean up over a four month period. The dry ice blasting process resulted in minimal debris and no damage to the parent structure. Surface sampling throughout this period verified the effectiveness of the cleaning methodology. The building was completed to the client’s satisfaction and the construction schedule was allowed to proceed with minimal delays.
|
 |
Upcoming PHH ARC Courses |
 |
| Course |
|
Location |
|
Date |
|
|
|
|
|
Asbestos Worker Training Course
Click here to Register. |
|
Saskatoon, SK |
|
Sept. 22-23, 2009 |
| |
|
|
|
|
Asbestos Worker Training Course
Click here to register. |
|
Regina, SK |
|
Sept. 24-25, 2009 |
| |
|
|
|
|
Management of Hazardous Materials in Building Renovation
Presented in Partnership with the VRCA
To register, click here. |
|
Vancouver, BC |
|
Oct. 6, 2009 |
| |
|
|
|
|
Fall Protection
Presented in partnership with CANPRO Training Resources
Click here for Registration Details. |
|
Coquitlam, BC |
|
Oct. 8, 2009 |
| |
|
|
|
|
Confined Space Awareness, Entry and Standby
Presented in partnership with CANPRO Training Resources
Click here for Registration Details. |
|
Coquitlam, BC |
|
Oct. 9, 2009 |
| |
|
|
|
|
Silica Control
Presented in Partnership with the VRCA
To register, click here. |
|
Vancouver, BC |
|
Oct. 22, 2009 |
| |
|
|
|
|
Management of Hazardous Materials in Building Renovation
Presented in Partnership with the VRCA
To register, click here. |
|
Abbotsford, BC |
|
Oct. 27, 2009 |
| |
|
|
|
|
Asbestos Surveyor Course
To register, click here. |
|
Vancouver, BC |
|
Oct. 29-30, 2009 |
| |
|
|
|
|
Environmental Management in Construction
Presented in Partnership with the VRCA
To register, click here. |
|
Vancouver, BC |
|
Nov. 4, 2009 |
| |
|
|
|
|
|
|
 |
PHH ARC Environmental Ltd. is a consulting and environmental services company that provides a wide range of environmental,
engineering, geosciences and health & safety solutions.
With over 25 years of experience, PHH ARC provides practical and professional services and solutions to ensure a better environment and
workplace, which gives our clients peace of mind.
PHH ARC Environmental Newsletter is designed to provide information of a general nature and is not intended as a substitute for professional consultation and advice in a particular matter. The opinions and interpretations expressed within are those of the author only and may not reflect those of other identified parties.
PHH ARC Environmental does not warrant the accuracy and completeness of this newsletter, nor endorse or make any representations about its content. In no event will PHH ARC Environmental be liable for any damages whatsoever arising out of the use of or reliance on the contents of this newsletter. |
 |
|
|
|
|