Click on the links below to view a project profile:

Environmental Assessment
Quesnel, BC

Multi-Phased Environmental Site Assessments
Calgary, Alberta

Industrial Hygiene Services
Edmonton, Alberta

Hazardous Materials Support Services
Wabamun, Alberta

Industrial Hygiene Services
Benzene Consulting

 


Environmental Assessment
Cariboo Pulp & Paper, Quesnel, BC

Project Start:
October 2009

Project Completion:
January 2010

Key Features:

  • Adherence to Federal requirements for Environmental Assessment
  • Expertise in comprehension and implementation of Natural Resources Canada Pulp and Paper Green Transformation Program (PPGTP) Guidelines
  • Wide Consultation requirements including Federal and Provincial Government and First Nations
  • Submission of an Screening Level Environmental Impact Statement (EIS) to satisfy the requirements of the Canadian Environmental Assessment Act (CEAA)

 

Client's Issue and Needs
Cariboo Pulp and Paper planned to implement a $12M upgrade to existing Mathieson Generators utilized to produce chlorine dioxide for bleaching pulp. Modernisation of these generators would enable the inclusion of a chemical recovery system which would result in higher efficiency of conversion of sodium chlorate to chlorine dioxide, a reduction in the loss of by products and elimination of SO2 from the process.

In order to be eligible for funding under the NR Can PPGTP, Cariboo Pulp and Paper we requirement to undertake a Screening Level Environmental Assessment in order to demonstrate that there were no long term negative environmental impacts of the proposed upgrades

All development is within the existing mill footprint, on land owned by the proponent.

Our Services and Solutions
PHH ARC attended a NR Can workshop in September 2009 in order to familiarize ourselves with the new guidance released by NR Can in June 2009.

PHH ARC undertook a Site visit to the Quesnel plant in order to meet with client representatives, assess the project footprint and examine the environmental baseline conditions.

Following a period of consultation with the BC Environmental Assessment Office, and First Nations Bands in the area, PHH ARC compiled a robust Environmental Impact Statement which included all stages of the process from Site Preparation to Decommissioning. All relevant project components and activities were assessed in terms of their impact upon key environmental components. Direct, indirect, cumulative and accidental impacts on the environment were all assessed.

A Notice of Commencement (NOC) of an Environmental Assessment was posted on the Canadian Environmental Assessment Registry in February 2010.



Multi-Phased Environmental Site Assessments
Industrial Sandblasting Facility, Calgary, AB

 

Project Start:
November 2008

Project Completion:
March 2010

Key Features:

  • Completion of multi-phased Environmental Site Assessments (ESAs) for pre-sale financing purposes.
  • Development of site-wide Phase II ESA Delineation program to determine extents of surficial metal impacts related to historical on-site sandblasting/ painting activities.
  • Development and completion of large-scale remedial action plan (RAP) to remediate confirmed surficial metal impacts.
  • Preparing final reports summarizing investigation findings for submission to lending institution.

 

Client's Issue and Needs
An industrial sandblasting facility located within the Foothills Industrial Business Park in Calgary, Alberta, had operated at this location since 1979. An attempt to sell the site by the owners resulted in a Phase I ESA request from the lending institution to satisfy the lenders internal risk department prior to releasing any funds to the potential purchaser.

The Phase I ESA identified various on-site and off-site areas of potential environmental concern, which resulted in various Phase II/III ESA investigations.

At the time of these assessments, the site continued to operate as a sandblasting facility. All on-site environmental investigation activities were coordinated with on-site personnel to ensure that disruptions to their day to day operations were kept to a minimum.

 

Our Services and Solutions
PHH ARC completed initial Phase I ESA and Phase II ESA investigations that identified localized petroleum hydrocarbon (PHC) impacts in soil related to fuel and waste oil aboveground storage tanks (ASTs). Remedial activities were completed to remove and properly dispose of these PHC soil impacts.

Initial investigation activities also identified localized PHC impacts to groundwater, possibly related to off-site activities at an adjacent auto wrecking yard. PHH ARC conducted a secondary Phase II ESA investigation to gather additional information for modifying the applicable Alberta Environment Tier 1 and 2 Soil and Groundwater Remediation Guidelines (2009) and eliminating the Domestic Use Aquifer (DUA) exposure pathway. Following elimination of the DUA exposure pathway, PHC concentrations in groundwater no longer exceeded the applicable criteria.

Phase II ESA activities also identified metal impacts in surficial soil across the majority of the site related to historical sandblasting and painting activities conducted on the site exterior. PHH ARC conducted an extensive Phase II ESA delineation investigation that involved drilling approximately 100 shallow boreholes across the entire site following a 10 m x 10 m grid and collecting soil samples at various depths to determine the vertical and horizontal extent of the metal impacts. Following completion of the delineation investigation, PHH ARC developed and implemented a RAP that involved approximately five weeks of on-site time overseeing the excavation of surficial soil impacted with metals across the majority of the site to depths ranging from 0.5 m to 1.0 m below ground surface (bgs). Field screening activities involved using a mobile X-Ray Fluorescence (XRF) device to determine approximate concentrations of metals on-site prior to laboratory submission and to aid in the determination of the final extents of the excavation.

Following completion of all investigation activities, formal reports were prepared and submitted to the client detailing the findings of the investigation and providing recommendations to aid in the prevention of future impacts on-site.

PHH ARC was responsible for coordinating all field activities to ensure work was completed in a timely and cost effective manner, while upholding the quality of the work completed.


Industrial Hygiene Services
Client Confidential - Edmonton, AB

 

Project Start:
August 2003

Project Completion:
June 2004

Key Features:

  • Compliance orders by Workplace Health & Safety.
  • Company ordered by Alberta Workplace Health & Safety to provide respiratory protection for all staff sorting recycled household materials.
  • Overall project management and performance of field duties

 


Client's Issue and Needs
Several workers were sent to the hospital after exposure to an unknown substance when sorting recycled household materials at the Edmonton facility.

Alberta Workplace Health & Safety closed the facility and ordered The Client to provide respiratory protection for all workers to protect them from future potential exposure.

The Client needed to reopen for business and their corporate assessments of similar facilities in North America were very different than that of the government.

Our Services and Solutions
PHH ARC met with the government and successfully lobbied for a step by step approach to address the potential for worker over exposure to chemicals when sorting the recycled materials.

Air monitoring was conducted which illustrated that under normal operating conditions there was a very low risk of exposure to chemicals during sorting the recycling materials.

Air monitoring was also conducted after ventilation upgrades were made by The Client. The data showed that the general air quality had improved.

Outcome
PHH ARC successfully brokered an action plan that allowed the client to reopen their facility.

Good industrial hygiene practices were followed, using engineering controls to protect the worker versus using the common approach of personal protective equipment which is the last resort.

The government was satisfied none of the worker's health and safety was at risk and their relationship with The Client improved.

An added bonus of the project was PHH ARC saved the client money.


Hazardous Materials Support Services
Client Confidential - Wabamun, AB

 

Project Start:
August 2006

Project Completion:
Summer 2008

Key Features:

  • Phased decommissioning and demolition of coal fired power plant.

  • Critical timing requirements.

  • Subsequent addressing of environmental issues.

  • Overall project management and performance of field duties of large scale asbestos abatement while other portions of plant still operating.

 


Client's Issue and Needs

The clients ’s desire to begin decommissioning of the Wabamun facility included very stringent timing and health and safety requirements.  As this was a phased process, with other parts of the plant remaining operational, ensuring cross-contamination did not happen and that the remediation contractors met all deadlines was of high importance.

PHH ARC was involved from the start, ensuring that the remediation contractor understood the level of care required by the client and that all timing requirements were fixed.

PHH ARC also helped resolve a number of environmental issues related to past remediations and historical storage of asbestos waste on the site.

PHH ARC is currently wrapping up Phase 2 of project on time.

Outcome

PHH ARC has ensured, and will continue to ensure that all work meeting high standards and that the clients’s needs for worker protection and project timing are met.

Good industrial hygiene practices were followed, using engineering controls to protect the worker versus using the common approach of personal protective equipment which is the last resort.

Industrial Hygiene Services
Client Confidential - Edmonton, AB

 

Project Start:
Summer 2005

Project Completion:
Summer 2005

Key Features:

  • Worker concerns over potential high levels of benzene and hydrocarbons
  • Unique hygiene approach
  • Tight client timelines

 


Client's Issue and Needs

The client was involved in numerous tunnel construction sites.  Initial testing at a site by a client found high volatile organic compound levels from soil vapour seepage and initial communication by client to staff suggested high benzene concentrations. 

Work stopped and client required an effective initial survey and ongoing monitoring approach to both ensure worker protection, but also allow work to continue.

Our Services and Solutions
PHH ARC combined traditional occupational hygiene sampling using sorbent tube sampling in combination with direct reading equipment equipped with benzene specific capabilities.  An initial side by side baseline of both methods allowed for confirmation that direct reading equipment was not giving false negative results. 

Outcome
The sampling strategy allowed for ongoing continuous monitoring of the site with a high level of confidence by both the client and their workforce that workers were not being overexposed. 

This combination of traditional approaches with innovative use of new equipment techniques allowed both the project to continue, but also save the client a great deal of money as opposed to traditional sampling techniques.

 


Home | About Us | Services | Sectors | Contact Us
©2008 | Copyright | Site Map | Disclaimer | Privacy Policy

Vancouver Web Development by Graphically Speaking

 
 
 
archives